Sample deliverable: material takeoff and bid review

This sample is made up. The house, the plans and every number below are invented to show the format and the kinds of differences a second look finds. Sample House: a 1-story ranch with a daylight basement and an attached 3-car garage, about 2,600 finished sq ft. Not a real plan set and not a real client.

1. Whole-house material takeoff (excerpt)

One line per material, foundation to shingles. Every line shows the plan sheet and detail it came from, the dimension or count used, and a confidence flag, so you can check any number in seconds. 12 of 142 lines shown.

TradeItemOrder qtySource: sheet, detail, dimension or countConf.
Excavation & fill3/4" crushed gravel under basement slab, 4"22.4 CYS-101 general note 4 (4" gravel); slab 1,650 SF measured on S-101; +10% compactionMed
Concrete & rebarFooting 20" x 10", tag F110.2 CYS-101 Footing Schedule, tag F1; 188 LF measured on S-101; +5%Med
Concrete & rebar#4 rebar x 20', footing21 sticksS-101 Footing Schedule F1, (2) #4 cont.; 188 LF x 2 + 10% lapsHigh
Sheathing7/16 OSB wall sheathing, 4x8142 sheetsS-201 shear wall schedule + A-201/A-202 elevations; sheeted walls 336.7 LF incl. gable endsMed
Windows & doorsWindow W3, 3050 single hung4 EAA-101 Window Schedule W3; count 4High
RoofingArchitectural shingle, 30-yr (spec sheet)34.2 SQS-401 roof plan, 2,860 SF plan area; 6/12 from section 2/A-301 (x1.118); +7%Med
RoofingIce and water shield8 rollsS-401 eaves 212 LF x 2 courses + valleys 48 LF. Extent not on plans or spec sheet: 2 courses assumedLow
Siding & trimLP lap siding 8" (spec sheet)2,450 SF netA-201/A-202 elevations: gross wall 2,980 SF less openings 530 SFMed
Soffit & fasciaVented soffit + 2x8 fascia308 LFS-401 eaves 212 LF + rakes 96 LF. Overhang not dimensioned: 24" scaled from 2/A-301Low
InsulationExterior wall cavity batts, 2x61,850 SFA-301 wall section 1; net wall SF. No R-value on plans: sized to code minimumLow
Drywall1/2" walls, 5/8" ceilings, 4x12312 sheetsA-101 floor plan, net wall + ceiling SF. Ceiling thickness not on plans: 5/8" assumedLow
Decks & porches2x10 PT deck joists @ 16", 14'28 EAS-102 deck framing plan, rear deck 36' wide: 36 x 12 / 16 + 1High
Order qty includes waste. High = read straight off the plans or a schedule. Med = measured or one step of math from plan data. Low = not on the plans or spec sheet: the assumption is written on the line and it goes on your questions list. Full sample: 142 lines, 88 High, 41 Med, 13 Low.
Questions before you order (from the Low lines): 1. Wall insulation R-value and product? 2. Gutter size, material and downspout count? 3. Ceiling drywall 1/2" or 5/8"? 4. Ice and water shield: how far up from the eaves? 5. Soffit overhang depth (not dimensioned)?

2. Wall LF, sheeted vs unsheeted

This split drives how framing and sheathing get priced, and it's the number generic takeoff shops usually don't give you. Here, two takeoffs of the same made-up plans are compared.

GroupSheeted?Takeoff A (LF)Takeoff B (LF)DiffWhy
Main house exteriorY198.0197.5+0.5Match
Garage exteriorY112.0111.7+0.3Match
Basement daylight wallY32.027.5+4.5A ran it corner to corner; B stopped at the concrete returns
Sheeted total342.0336.7+1.6%
Main interiorN171.5152.0+19.5A counted the 18' kitchen counter line (M-I08) as a wall; B didn't
Basement furringN148.0139.5+8.5A ran furring through the door and the egress wells
Basement interiorN120.0124.0-4.0Small closet and stub differences
Unsheeted total439.5415.5+5.8%Most of it is one line: M-I08
All walls781.5752.2+3.9%

Same plans, two takeoffs, 29 LF apart. Neither is wrong until someone decides whether the counter line is a wall and where the daylight wall stops. If your vendors made different calls, their totals aren't comparable, and nobody tells you.

3. Numbered wall list (excerpt)

Every wall gets a number, a length, a plate height, a stud size and a sheeted call. 12 of the 61 rows shown.

Wall #LevelLocationLengthPlate htStudsSheeted
M-E01MainFront wall, living room34'-0"9'-1 1/8"2x6 @ 16"Y
M-E02MainSide wall, primary suite26'-6"9'-1 1/8"2x6 @ 16"Y
M-E06MainRear wall, great room gable22'-0"9'-1 1/8" *2x6 @ 16"Y
M-E09MainEntry porch wall9'-4"9'-1 1/8"2x6 @ 16"Y
G-E01GarageGarage front, (1) 16x8 + (1) 9x8 OH doors33'-0"10'-1 1/8"2x6 @ 16"Y
G-E02GarageGarage side wall24'-0"10'-1 1/8"2x6 @ 16"Y
B-E01BasementDaylight wall on 4' stem27'-6"8'-1 1/8"2x6 @ 16"Y
M-I02MainHall, bearing30'-0"9'-1 1/8"2x6 @ 16"N
M-I05MainBedroom 2 / bath11'-0"9'-1 1/8"2x4 @ 16"N
M-I08MainKitchen counter line, (1) 6' opening18'-0"9'-1 1/8"2x4 @ 16"N ?
M-I11MainPantry, low-confidence read5'-2"9'-1 1/8"2x4 @ 16"N ?
B-F01BasementFurring on concrete, family room24'-0"8'-1 1/8"2x4 @ 16"N
* Flagged: M-E06 is a tall gable wall whose height isn't dimensioned on the plans. "N ?" = judgment call flagged for the buyer.
Schematic wall-number plan Generic house outline. Exterior walls in red are sheeted, interior walls in blue are unsheeted, each wall carries a tag like M-E01. One amber dashed counter line is flagged as a judgment call. M-E01 M-E05 M-E09 M-E13 G-E01 M-I03 M-I04 M-I09 M-I12? GARAGEBEDGREAT RMKITCHEN SCHEMATIC ONLY. NOT A REAL PLAN SET.
SheetedUnsheetedParty / fire wall
Schematic for illustration. The real deliverable is your own plan sheets with every wall tagged in color.

What comes with the wall list

  • Building SF by area (main, basement, garage, porches, decks) with a measured-vs-stated check
  • Perimeter check: main exterior 198.0 LF measured against the overall dimensions
  • Studs, plates, PT sill, sheathing, headers by tag, beams, posts and hardware from the plan schedules
  • A flags list: undimensioned heights, untagged headers, low-confidence reads, possible typos on the plans

4. Where the two takeoffs disagreed

These are the same kinds of differences that hide inside vendor quotes. A review puts them on the table.

ItemTakeoff ATakeoff BWhat happened
Counter-line wall (M-I08)18 LF0Is an 18' line with a 6' opening a wall or a cabinet run? Needs a decision, not a guess.
Glulam, 5-1/8 x 1246 LF30 LFA ran the full porch beam. B left the center 16' to the timber truss package. Same beam, two packages. Easy to buy twice or not at all.
Timber trusses12A missed the rear patio gable timber truss.
Holdowns64A counted 2 holdowns tagged with a model that isn't in the hardware schedule. Likely a plan typo. A question for the engineer, not the yard.
Joist hangers1428A hung the porch joists at one end only.
Anchor bolts120omittedB treated them as foundation contractor scope. Fine, if the foundation contractor knows that.
Wall sheathing, 7/16 OSB128 sheets142 sheetsA left the gable wall at plate height and missed gable-end truss sheathing.
Headers22 openings18 openingsA assigned headers to 4 untagged openings and flagged them as assumptions.

In this made-up example, Takeoff A plays the part of an unchecked first pass. Every one of these misses is on my checklist, because first passes miss things and the check is the job.

5. What a bid review sheet looks like

Example layout with made-up vendors on a lumber package. Roofing, siding, window and concrete quotes get their own scope lines. Every scope line gets a call for every quote, and every Excluded or Unclear line gets a cost added before totals are compared.

Scope lineVendor AVendor BVendor C
Wall sheathingIncludedIncludedExcluded
Headers and rough openingsIncludedIncludedIncluded
Loose beams and posts (glulam, LVL)By othersUnclearIncluded
Structural hardware (holdowns, hangers, straps)"Per plan"ExcludedIncluded
Anchor boltsExcludedExcludedUnclear
Engineering / sealed calcsIncludedExcludedIncluded
DeliveryFlat, 1 tripPer load × milesIncluded
Roof sheathingIncludedExcludedIncluded
Deposit / balance20% / on delivery50% / on delivery30% / net 15
Price hold30 days15 daysNot stated
Drawing revisions1 includedBilled hourlyUnclear
Illustration only. Not from real quotes. In the real workbook each line also carries my local cost for the gap, and the sheet ends with an adjusted total, a unit cost and a rank.